Friday, 31 May 2013

It's started!


Here we go then - we're off! Quite a dramatic start to be fair. The builders have certainly made their mark over the first few days. 

Don't worry though - the whole site is securely fenced off so the children will be totally safe. 

We'll update you regularly so keep popping back. 

Tuesday, 28 May 2013

Here it is - our new entrance.

This is our temporary entrance for the last half term. Parents can take children in Yr R, 1 and 2 to their classrooms through this entrance. Children in Years 3, 4, 5 and 6 are being asked to walk to class on their own. 

The office team will be staffing this new entrance throughout the day so it's business as usual. 

 The builders started in site today - photos to follow ... 

Wednesday, 22 May 2013

Off we go !


Here is a quick glimpse of the work starting on our new entrance. It will definitely be finished in time for the start of school after the holidays. 

More photos to follow ...

Wednesday, 15 May 2013

As you were ...

Don't worry folks, we're all back on track now. The builders will move in over half term so the new entrance and the new fire plan will start when we get back. 

We'll try to post some photos over half term so it's not too much of a shock when you get back! 

Friday, 10 May 2013

Hold your horses!

We're sad to say that the start of our building work is going to be slightly delayed. There is a technical hitch with getting supplies to school to start the work.

We'll update you when we have more information. Sorry for any confusion.

Wednesday, 8 May 2013

Where did the office go?

All change!

This is a map showing our new entry point while the builders are working on site.
There will be a temporary entrance and reception built at the very top of the school, behind the minibus garage. The entrance will be staffed all day and you will be able to use it just like the old one!

Unfortunately, the corridor being used is quite narrow, so we are asking that children in Years 3, 4, 5 and 6 are dropped off at the entry point and then walk themselves to class.

This entrance will start to be used on Monday 13th May - next Monday!

Ms Filer and Mr Robinson will be on hand first thing Monday morning to make sure everything goes smoothly.


Any problems, just ask! 

Thursday, 2 May 2013

New Fire Plan

New Fire Plan

Here is our brand new fire plan. We will use this plan for the rest of the term once the builders arrive on the 13th. All of the children have been shown the plan in assembly and have talked about it in their classes.

We will be practicing it several times during the first few days of the project so that all of the staff and children are aware of what to do in the event of a fire.


Please read our new plan carefully